Who Could Replace Marnus Labuschagne for Australia? The Options Explained
Who could replace Marnus Labuschagne at No. 3 for Australia? Compare Josh Inglis, Steve Smith, Sam Konstas, Nathan McSweeney and other Test options.
Snowy Hydro 2.0 could cost A$25 billion, but that figure is a higher-cost scenario, not the project's current target or the amount already spent. In its October 22, 2026 reassessment, Commonwealth-owned Snowy Hydro set a new target project cost of A$22.2 billion, with an allowance for a possible A$25 billion outcome. The company also moved its goal for full commissioning to late 2029. Australian ministers acknowledged the revised estimates on October 23. These are figures in Australian dollars, not U.S. dollars.
The distinction matters for anyone searching for the “Snowy Hydro 2.0 budget.” A construction cost forecast, spending to date, Commonwealth equity, and government loans answer four different financial questions. This guide separates them, explains the cost increases, and shows where to check the next official update. The figures below reflect the October 2026 reassessment and the most recent relevant public audit available for this review.
| Figure | What it means | Source and period |
|---|---|---|
| A$22.2 billion | Current target for total project delivery cost, rather than remaining expenditure alone. | Snowy Hydro reassessment, October 22, 2026 |
| A$25 billion | Higher-cost scenario allowing for project risks and estimation uncertainty; not a confirmed final bill. | Snowy Hydro reassessment, October 22, 2026 |
| A$12 billion | Previous total project cost target established at the 2023 reset; now superseded. | Snowy Hydro announcement, August 31, 2023 |
| A$11.1 billion | Project expenditure recorded as of March 31, 2026. This is an earlier spending snapshot, not a November 2026 total. | Australian National Audit Office, June 18, 2026 |
The gap between the new target and the higher scenario is A$2.8 billion. The increase from the 2023 A$12 billion target to the new A$22.2 billion target is A$10.2 billion. Neither difference should be mistaken for a new appropriation that has already been paid to the project.
For the official starting point, read Snowy Hydro's October 2026 cost reassessment and the Australian government's October 23 ministerial statement.
The much-quoted A$2 billion figure relates to the project's early public announcement in 2017. It is useful background on how expectations changed, but it was not the same kind of developed, fully scoped delivery estimate as the later investment-decision and construction forecasts. Treating every number as an identical budget baseline can make the history look simpler than it was.
The Australian National Audit Office's June 2026 performance audit records that the 2018 final investment decision estimated A$5.9 billion excluding exploratory work, or A$6.1 billion including early work. Snowy Hydro then reset the project in August 2023 with a revised A$12 billion total target and a December 2028 target for all units to enter commercial service. The latest October 2026 estimate replaces that target, and full commissioning is now targeted for late 2029.
There is an important boundary to the comparison: the ANAO notes that the project's own cost reporting excludes some government oversight expenses and related transmission developments. The A$25 billion scenario should therefore not be described automatically as the complete cost of every associated electricity-network upgrade.
The October reassessment identifies several overlapping causes. Each affects cost differently, and no verified breakdown assigns a precise percentage of the total overrun to every factor.
Snowy 2.0 is being built underground in challenging terrain. Detailed engineering work has continued to reveal tasks and complexity that were not fully defined when the final investment decision was taken. Tunnel boring, excavation, ground conditions, and the underground power station require more time and resources when actual conditions differ from plans. Snowy Hydro said construction design had reached 96% completion by the October update, versus 44% at the 2023 reset; greater design maturity does not eliminate all remaining construction risk.
Snowy Hydro said principal contractor Future Generation Joint Venture had not achieved expected productivity and had previously underestimated parts of the delivery scope. The contract structure changed during the 2023 reset from an earlier fixed-price approach to a target-cost arrangement with incentives and reimbursable elements. That makes contractor performance and effective oversight particularly important to the project's ultimate cost.
Global escalation for equipment, skilled people, and services exceeded assumptions made at the 2023 reset. When a large construction program stretches over additional years, prolonged staffing, supervision, machinery, and supply-chain requirements can increase the total. The company describes the latest assessment as a response to the combined effects of these pressures, rather than a single newly discovered fault.
The ANAO's report, published June 18, 2026, is useful because it is separate from the project owner's financial case. It judged Snowy Hydro's project management partly effective and identified deficiencies in cost forecasting, project controls, the agreed schedule baseline, and the use of performance incentives. It warned that delivery and cost risk was increasingly concentrated on the Commonwealth-owned business and, ultimately, its government shareholder.
That audit examined earlier project management and spending data, not the final October reassessment. It should not be presented as having endorsed the A$22.2 billion target or A$25 billion scenario. Conversely, Snowy Hydro says it has since strengthened oversight through outside construction experts, a contractor project-control office, board-level monitoring, and leadership changes. Readers should track both later implementation evidence and fresh independent review, rather than treating either announcement as proof that all cost risks are resolved.
There is no verified basis to say Australian taxpayers have already paid A$25 billion. The figure refers to a potential total construction cost, while financing combines different instruments. Snowy Hydro is a Commonwealth-owned government business enterprise, not a department funded solely by annual grants.
According to the October 22 statement, the Commonwealth's preferred capital strategy for the revised project cost was still being developed. Therefore, the final split of additional equity, borrowing, and company funding had not been confirmed in the sources reviewed. To assess the taxpayer exposure accurately, look for subsequent budget papers, shareholder announcements, loan terms, and audited financial statements rather than dividing A$25 billion by Australia's population.
The project connects the existing Tantangara and Talbingo reservoirs in New South Wales through tunnels and an underground pumped-hydro power station. During lower-demand or lower-priced periods, electricity pumps water uphill. When demand rises, water flows downhill through turbines to generate electricity. It is primarily a large energy-storage system; pumping consumes energy, so it is not a source of free net electricity.
Snowy Hydro's published design specifies approximately 2,200 megawatts (MW) of generation capacity and 350,000 megawatt-hours (MWh), or 350 gigawatt-hours, of energy storage. MW measures the rate at which the plant can deliver electricity at a given time; MWh measures the amount it can deliver over a period. The storage volume equates to roughly 160 hours of generation at maximum output, subject to operating conditions and available stored water.
In its 2026 Integrated System Plan, the Australian Energy Market Operator describes the importance of generation, transmission, storage, and backup supply as coal stations retire. Long-duration storage can help cover extended periods of low wind or solar output, which is a different task from balancing a few hours of demand. Snowy 2.0 is intended to be one part of that wider system, not a substitute for all other power plants, batteries, or transmission lines.
Not in a direct or easily calculated one-for-one way. Construction cost and household retail tariffs are different measures. Electricity bills also depend on wholesale markets, networks, retailer costs, regulations, and consumption. Snowy Hydro has pointed to commissioned economic modeling suggesting the completed project could reduce total wholesale electricity costs by more than A$7 billion through 2075 and create wider economic benefits. Those figures are projections based on modeling assumptions, not savings already delivered or a guaranteed discount on every customer's bill.
To evaluate value for money, compare the eventual capital cost, financing and operating costs, market revenue, reliability benefits, electricity price effects, and alternatives available at the same time. Potential benefits from long-duration storage may be substantial; the growing bill and delivery delays still deserve independent scrutiny. Both points can be true.
The search for a “Snowy Hydro 2.0 A$25 billion budget” is responding to a real, officially announced cost reassessment. As reported in October 2026, A$22.2 billion is the project's target total cost and A$25 billion is a higher-cost scenario. The project is being built to provide exceptional long-duration electricity storage, but its escalating cost, construction risks, and unfinished financing arrangements are legitimate questions. The most useful next evidence will be a detailed new funding plan and independently verifiable progress toward late-2029 commissioning.
Who could replace Marnus Labuschagne at No. 3 for Australia? Compare Josh Inglis, Steve Smith, Sam Konstas, Nathan McSweeney and other Test options.
Why is Snowy Hydro 2.0 linked to A$25 billion? Compare its A$22.2 billion cost target, higher-risk scenario, delays, funding, and energy benefits.
How could Australian power poles support more EV charging? Explore the 2026 federal rollout, AC and DC chargers, parking limits, costs, and local availability.
Learn what UK indefinite leave to remain (ILR) means, who qualifies, application costs, residence rules, citizenship options, and 2026 policy updates.
Check November 2026 Premium Bonds results on November 3 with NS&I's official website or app. Find holder numbers, missing prizes, and payment options.
Learn how a cyberattack can disrupt supermarket freezers, what Europe's 2026 incidents confirm, and how retailers protect food safety and shoppers.
Discover what Zelda: Ocarina of Time is, how to start playing, essential beginner tips, and how the 1998 classic compares with the 2026 Switch 2 remake.
Will your area have a white Christmas in 2026? Learn where to check NOAA snow odds, when local forecasts become useful, and how to read snowfall alerts.
Learn what SpaceX does, how Falcon 9, Dragon, Starship and Starlink work, and what is already operational versus still in development.
The 2026 US midterm elections take place November 3. Learn which seats are at stake, how Congress may change, and why the outcome matters to Australia.